Monday, September 6, 2010

Project Progress of 11 Units at Permai Jaya - September First Week

2nd Sep


Construction completed. Awaiting CoF.


1 Final Unit left. 
Price RM218k.
Call Mr. Shaker at 0193754905 if interested.

Wednesday, August 11, 2010

Project Progress of 11 Units at Permai Jaya - August Second Week

10th Aug


Front View

Gates painted.

Back View

Finished internal and external painting and tiling.

Monday, August 2, 2010

Wednesday, July 28, 2010

Project Progress of 11 Units at Permai Jaya - July Final Week

July 28th


Front View


Back View

Installed all Front Gates.
Finishing up internal tiling.
Back perimeter fencing in progress.