Wednesday, June 30, 2010

Project Progress of 11 Units at Permai Jaya - June Final Week

June 28th


Front View


Back View

Plastering all done. Divider walls erected. 
Preparing for roadworks outside.



Finished laying master bedroom tiles.

Wednesday, June 16, 2010

Project Progress of 11 Units at Permai Jaya - June 3rd Week

June 16th

Front View.

Back View.

Finishing up the external plastering work for back and front.


Construction of 1st floor plaster ceiling in progress.


1st floor toilet floor tiling done.


Preparing upper bedroom flooring for tiling.

Tuesday, June 15, 2010

Taman Permai Jaya Update

3 Units Left!!!

Contact us before all the units are sold out.
Only intermediate units left.

Details:
Built Up Area: 1816 sq ft
Bedrooms: 4
Bathrooms : 3
Freehold

Unit 1
20' x 99'
Price: RM220,000

Unit 2
20' x 102'
Price: RM223,000

Unit 3
20' x 111'
Price: RM229,000

Interested? Contact our Marketing Manager Mr. Shekar at 019-3754905 now.




Wednesday, June 9, 2010

Project Progress of 11 Units at Permai Jaya - June 2nd Week

June 9th



Front View.

Current focus is on the internal tiling, plastering and fittings.


Sanitary ware in downstairs toilet installed. 
Floor tiling in progress.




Staircase railing design.




Back view. Starting back plastering for end lot.


Tuesday, June 1, 2010

Project Progress of 11 Units at Permai Jaya - June First Week

May 31st



Front View.
Front external plastering done.

View from the 1st Floor.


Wall tiling of Master bedroom toilet in progress.
Wall tiles up to 5ft high.




Divider railing design.

External plastering at the back in progress.