Wednesday, July 28, 2010

Project Progress of 11 Units at Permai Jaya - July Final Week

July 28th


Front View


Back View

Installed all Front Gates.
Finishing up internal tiling.
Back perimeter fencing in progress.

Friday, July 23, 2010

Project Progress of 11 Units at Permai Jaya - July Third Week

July 22nd

Front View



Front View 2

Landscape trees planted. 
Installation of front gates in progress.


Preview of paint job on house.

Thursday, July 15, 2010

Project Progress of 11 Units at Permai Jaya - July Second Week

July 12th

Front View from Left

Back View

July 13th

Front View
Performing concreting for driveway.

Staircase tiling.

Friday, July 9, 2010

Project Progress of 11 Units at Permai Jaya - July First Week [2]

July 8th

Front view
Houses base coat painted.
Indoor stairs tiling in progress.


Back yard walk way in progress.

Tuesday, July 6, 2010

Project Progress of 11 Units at Permai Jaya - July First Week

July 6th


Front View - Left Side


Front View - Right Side


Back View





Preparation for road works in progress. Starting to paint base coat.
Completing drains serving the buildings. Completing 1st floor tiling.