Project Progress of 11 Units at Permai Jaya - June 2nd Week

June 9th



Front View.

Current focus is on the internal tiling, plastering and fittings.


Sanitary ware in downstairs toilet installed. 
Floor tiling in progress.




Staircase railing design.




Back view. Starting back plastering for end lot.